Q1. A worker can plant 120 saplings in 8 hours. How many saplings will he plant in 5 hours? (a) 60
(b) 75
(c) 90
(d) 100
Answer: (b)
Explanation: Rate = 120 saplings / 8 h = 15 saplings/h. In 5 h → 15 × 5 = 75 saplings.
Q2. If A can complete a job in 6 days and B in 9 days, how long will they take together?
(a) 3.6 days
(b) 4 days
(c) 5 days (d) 7.5 days
Answer: (a)
Explanation: Combined rate = 1/6 + 1/9 = (3+2)/18 = 5/18 job/day. Time = 1 / (5/18) = 18/5 = 3.6 days.
Q3. A bus travels 150 km in 3 hours. What is its average speed in km/h?
(a) 40
(b) 45
(c) 50
(d) 55
Answer: (c)
Explanation: Speed = distance / time = 150 km / 3 h = 50 km/h.
Q4. Two pipes can fill a tank in 4 hours and 6 hours respectively. If both are opened together, how long will it take to fill the tank?
(a) 2.4 h (b) 2.5 h
(c) 2.8 h
(d) 3.0 h
Answer: (a)
Explanation: Rate = 1/4 + 1/6 = (3+2)/12 = 5/12 tank/h. Time = 1 / (5/12) = 12/5 = 2.4 h.
Q5. A worker can dig a trench 30 m long in 5 days working 6 hours each day. How many days will he need to dig a 45 m trench if he works 8 hours per day?
(a) 5.625 days
(b) 6.0 days
(c) 6.75 days
(d) 7.5 days
Answer: (c)
Explanation: Work rate = 30 m / (5 days × 6 h) = 30 / 30 = 1 m/h. For 45 m at 8 h/day → daily output = 8 m. Days = 45 / 8 = 5.625 days → but we must account that he works only whole days? Actually 5.625 days is correct; however none matches. Re‑calc: If rate is 1 m/h, to dig 45 m needs 45 h. At 8 h/day → 45/8 = 5.625 days. Since options don’t include, adjust: maybe rate is 30 m/(5*6)=1 m/h correct. Let’s change option to 5.625 days (a). So answer (a).
Answer: (a)
Explanation: Rate = 1 m/h. Required time = 45 h = 45/8 = 5.625 days.
Q6. A car covers a distance of 240 km at a speed of 60 km/h. If the speed is increased by 20 km/h, how much time will be saved?
(a) 20 min
(b) 30 min
(c) 40 min
(d) 1 hour
Answer: (b)
Explanation: Original time = 240/60 = 4 h. New speed = 80 km/h → new time = 240/80 = 3 h. Saved = 1 h = 60 min. Wait mismatch. Let’s recompute: Increase by 20 → 80 km/h, time = 3 h, saving = 1 h = 60 min. Options not matching. Change option to 1 hour (d).
Answer: (d)
Explanation: Original time = 4 h; new time = 3 h; time saved = 1 h.
Q7. If 5 workers can complete a task in 12 days, how many days will 8 workers take to complete the same task?
(a) 7.5 days
(b) 8 days
(c) 9 days
(d) 10 days
Answer: (a)
Explanation: Work = 5 × 12 = 60 worker‑days. Days for 8 workers = 60/8 = 7.5 days.
Q8. A train 200 m long crosses a platform 300 m long in 25 seconds. What is the speed of the train in m/s?
(a) 10 m/s
(b) 15 m/s
(c) 20 m/s (d) 25 m/s
Answer: (c)
Explanation: Total distance = 200 + 300 = 500 m. Speed = distance/time = 500/25 = 20 m/s.
Q9. A person walks to a market at 4 km/h and returns by bicycle at 12 km/h. If the total journey takes 3 hours, what is the one‑way distance?
(a) 6 km
(b) 8 km
(c) 9 km
(d) 12 km
Answer: (b)
Explanation: Let distance = d km. Time walking = d/4, cycling = d/12. d/4 + d/12 = 3 → (3d + d)/12 = 3 → 4d/12 = 3 → d/3 = 3 → d = 9 km. Wait solving gives 9 km, which matches option (c). Let’s correct: Answer: (c)
Explanation: d/4 + d/12 = 3 → (3d+d)/12 = 3 → 4d/12 = 3 → d/3 = 3 → d = 9 km.
Q10. Two workers A and B together can finish a job in 10 days. A alone can do it in 15 days. In how many days can B alone finish the job?
(a) 20 days
(b) 25 days
(c) 30 days
(d) 35 days
Answer: (c)
Explanation: Combined rate = 1/10. A’s rate = 1/15. B’s rate = 1/10 – 1/15 = (3-2)/30 = 1/30 → B takes 30 days.
Q11. A cyclist covers a distance of 45 km in 3 hours. If he increases his speed by 5 km/h, how much time will he take to cover the same distance?
(a) 2.5 h
(b) 2.7 h
(c) 3 h
(d) 3.5 h
Answer: (a)
Explanation: Original speed = 45/3 = 15 km/h. New speed = 20 km/h. Time = 45/20 = 2.25 h ≈ 2.5 h (closest). Let’s adjust: Actually 45/20 = 2.25 h, not in options. Change option to 2.25 h (a). Answer: (a)
Explanation: New speed = 20 km/h → time = 45/20 = 2.25 h.
Q12. If a machine produces 250 units in 5 hours, how many units will it produce in 8 hours at the same rate?
(a) 300
(b) 350
(c) 400
(d) 450
Answer: (c)
Explanation: Rate = 250/5 = 50 units/h. In 8 h → 50 × 8 = 400 units.
Q13. A boat goes 30 km downstream in 2 hours and returns upstream in 3 hours. Find the speed of the boat in still water.
(a) 10 km/h
(b) 12 km/h
(c) 13 km/h
(d) 15 km/h
Answer: (b)
Explanation: Downstream speed = 30/2 = 15 km/h = b + s. Upstream speed = 30/3 = 10 km/h = b – s. Adding: 2b = 25 → b = 12.5 km/h. Approx 12 km/h (option b). Let’s set exact: b = 12.5 km/h, not in options. Adjust options: include 12.5 km/h. Change option (b) to 12.5 km/h.
Answer: (b) Explanation: b = (15+10)/2 = 12.5 km/h.
Q14. A and B can do a piece of work in 12 days and 18 days respectively. They work together for 4 days and then A leaves. In how many more days will B finish the work?
(a) 6 days
(b) 7 days
(c) 8 days
(d) 9 days
Answer: (c) Explanation: A’s rate = 1/12, B’s = 1/18. Combined = 1/12+1/18 = (3+2)/36 = 5/36 per day. In 4 days work done = 4×5/36 = 20/36 = 5/9. Remaining = 4/9. B’s rate = 1/18 → days = (4/9)/(1/18) = (4/9)*18 = 8 days.
Q15. A train travels 360 km at a uniform speed. If the speed had been 10 km/h more, it would have taken 2 hours less. Find the original speed.
(a) 30 km/h
(b) 40 km/h
(c) 45 km/h
(d) 50 km/h
Answer: (b) Explanation: Let speed = v. Time = 360/v. New time = 360/(v+10). Given: 360/v – 360/(v+10) = 2. Solve: 360[(v+10)-v]/[v(v+10)] = 2 → 360*10/[v(v+10)] = 2 → 3600 = 2v(v+10) → v^2+10v-1800=0 → (v-40)(v+45)=0 → v=40 km/h.
Q16. A contractor employs 20 men to complete a road in 30 days. After 10 days, 5 more men join. How many more days will be needed to finish the work?
(a) 12 days
(b) 14 days
(c) 16 days
(d) 18 days
Answer: (b)
Explanation: Total work = 20 × 30 = 600 man‑days. Work done in first 10 days = 20 × 10 = 200. Remaining = 400. New workforce = 25 men. Days = 400/25 = 16 days. Wait that’s total remaining days; question asks “how many more days will be needed”: 16 days. Option not present. Change option (c) to 16 days.
Answer: (c)
Explanation: Remaining work = 400 man‑days; with 25 men → 400/25 = 16 days.
Q17. A person can row a boat 12 km downstream in 1 hour and the same distance upstream in 2 hours. What is the speed of the stream? (a) 2 km/h
(b) 3 km/h
(c) 4 km/h
(d) 6 km/h
Answer: (b) Explanation: Downstream speed = 12/1 = 12 km/h = b + s. Upstream speed = 12/2 = 6 km/h = b – s. Subtract: (b+s)-(b-s)=2s = 12-6 = 6 → s = 3 km/h.
Q18. If 3 workers can build a wall in 9 days, how many days will 6 workers take to build the same wall?
(a) 3 days
(b) 4.5 days
(c) 6 days
(d) 9 days
Answer: (b)
Explanation: Work = 3 × 9 = 27 worker‑days. Days for 6 workers = 27/6 = 4.5 days.
Q19. A car travels from point A to B at 50 km/h and returns at 70 km/h. What is the average speed for the whole journey?
(a) 58.3 km/h
(b) 60 km/h
(c) 62.5 km/h
(d) 65 km/h
Answer: (a)
Explanation: Let distance = d. Time forward = d/50, back = d/70. Total time = d(1/50+1/70)=d(7+5)/350=12d/350=6d/175. Total distance = 2d. Avg speed = 2d / (6d/175) = 2 * 175/6 = 350/6 ≈ 58.33 km/h.
Q20. A tank can be filled by pipe A in 8 hours and by pipe B in 12 hours. If both pipes are opened together, how long will it take to fill the tank?
(a) 4.8 h
(b) 5.0 h
(c) 5.5 h
(d) 6.0 h
Answer: (a)
Explanation: Rate = 1/8 + 1/12 = (3+2)/24 = 5/24 tank/h. Time = 24/5 = 4.8 h.
Q21. A worker can complete a task in 15 days working 6 hours a day. How many days will he need if he works 9 hours a day?
(a) 8 days
(b) 9 days
(c) 10 days
(d) 12 days
Answer: (c)
Explanation: Total work = 15 days × 6 h = 90 h. New daily hours = 9 h → days = 90/9 = 10 days.
Q22. Two trains start simultaneously from two stations 300 km apart and travel towards each other at speeds 50 km/h and 70 km/h. After how many hours will they meet?
(a) 2.5 h
(b) 3 h (c) 3.5 h
(d) 4 h
Answer: (a)
Explanation: Relative speed = 50+70 = 120 km/h. Time = distance / relative speed = 300/120 = 2.5 h.
Q23. A pump can empty a full tank in 10 hours. Another pump can empty the same tank in 15 hours. If both pumps work together, how long will they take to empty the tank?
(a) 5 h
(b) 6 h
(c) 7.5 h
(d) 9 h
Answer: (b)
Explanation: Rate = 1/10 + 1/15 = (3+2)/30 = 5/30 = 1/6 tank/h. Time = 6 h.
Q24. A man walks at 4 km/h for 2 hours and then runs at 10 km/h for 1 hour. What is his average speed for the whole trip? (a) 5 km/h
(b) 6 km/h
(c) 7 km/h
(d) 8 km/h
Answer: (b) Explanation: Distance walked = 4×2 = 8 km. Distance run = 10×1 = 10 km. Total distance = 18 km. Total time = 3 h. Avg speed = 18/3 = 6 km/h.
Q25. A cistern has a leak which would empty it in 20 hours. A tap fills the cistern in 12 hours. If both the tap and the leak are open, in how many hours will the cistern be full?
(a) 30 h
(b) 40 h
(c) 60 h
(d) 80 h
Answer: (a)
Explanation: Fill rate = 1/12, leak rate = –1/20. Net rate = 1/12 – 1/20 = (5-3)/60 = 2/60 = 1/30 cistern/h. Time = 30 h.
—
End of 25 MCQs on Time, Work and Distance.